NH Route 28 Water Main Projects

Southern NH Regional Water Projects S1A and S1B

General Info

Lead Department: Municipal Services Department - Engineering Division

Project Manager: Dan Hudson, Director Of Engineering

Contractor: Revoli Construction Co., Inc.

Design Engineer: Weston & Sampson Engineers, Inc.

Funding: NH MtBE Settlement Funds and the NH Drinking Water and Groundwater Trust Fund (DWGTF)

Contract S1A Construction Contact: Georges Harb, Weston & Sampson - Resident Engineer at (603) 548-9181 or HarbG@wseinc.com with questions.

Contract S1B Construction Contact: Manny Manganais, Weston & Sampson - Resident Engineer at (978) 587-5125 with questions.

Project Details

These are two Contracts (S1A and S1B) which are part of the Southern New Hampshire Regional Water (SNHRW) Project. Work for these Contracts includes the installation of approximately 17,000 linear feet of 16-inch and 20-inch ductile iron water main, meter pit, valves, hydrants, and other appurtenances on Rockingham Road (NH Route 28) in the towns of Windham and Salem.

Public Notices

2019.10.21 - NH Route 28 Water Main Public Notice

Project Updates

2019.11.20 - NH Route 28 Water Main Progress Report

2019.11.01 - NH Route 28 Water Main Progress Report

2019.10.15 - NH Route 28 Water Main Progress Report